| File Note: |
The reply of the industry has been perused and it was observed as under:
1. The industry has applied for obtaining CTO in the name of Sh. Rahul Sharma, Partner, not in the name of Consultant hired by it. As such, the industry is required to submit the authority letter in the name of Sh. Rahul Sharma, Partner.
2. As per the electricity bill, the industry has started its operations in the month of April 2025. As such, the industry is required to deposit the penalty @ 100% of one year fee under the both Acts.
3. As per the Policy of the Board, the consent fee needs to be calculated after considering the lease value of land, building and machinery. As such, after considering the lease value of land and building for 05 years, the total value of fixed assets becomes Rs. 218.25 lacs due to which the fee slab has been changed. As such, the industry is required to deposit the consent fee considering the fee slab of Rs. 200.00 lacs to Rs. 500.00 lacs.
4. The reply w.r.t. e-stamp number mentioned on the lease deed differs from the e-stamp number mentioned on the affidavit is not satisfactory.
5. The industry has submitted the completion of ETP; however, it has not submitted the completion certificate alongwith drawing of APCD installed with the boiler.
As such, the application cannot be processed further and is hereby returned with request to resubmit the application after attending the above said observations. |