| Id: | 31509664 |
| Approve: | false |
| Approve Note: | |
| Clarification: | true |
| Clarification Note: | It is submitted that the application was scrutinzed and it was observed that the HMP has not submitted proof of date of commissioning and also not submitted compliance report of NOC (CTE). The industry is requested to clarify the above within 03 days. |
| Date Created: | 2026-03-19 08:01:42.574 |
| File Note: | It is submitted that the application was scrutinzed and it was observed that the HMP has not submitted proof of date of commissioning and also not submitted compliance report of NOC (CTE). The industry is requested to clarify the above within 03 days. |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB214 |
| Reject: | false |
| Reject Note: | |
| Role: | RO AEE Harblisterjeet Singh |