| Id: | 31520545 |
| Approve: | false |
| Approve Note: | |
| Clarification: | true |
| Clarification Note: | While scrutinizing the application, it was observed that the HCF has not submitted approved building plan and land documents indicating details of the property. Therefore, you are requested to submit the above said documents within 02 days. |
| Date Created: | 2026-03-19 22:52:29.162 |
| File Note: | While scrutinizing the application, it was observed that the HCF has not submitted approved building plan and land documents indicating details of the property. Therefore, you are requested to submit the above said documents within 02 days. |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB197 |
| Reject: | false |
| Reject Note: | |
| Role: | RO JEE Ritakshi Dhariwal |