Id: 31622886
Approve: false
Approve Note:
Clarification: false
Clarification Note:
Date Created: 2026-03-31 19:37:47.77
File Note: What is the total area before and after expansion. Whether the project is covered under the purveiw of EIA notification dated 14.09.2006 after expasnion...... built up area after expansion. Whether the present CTE is valid and fee calculated accordingly. Give the detail of the total area available for disposal of the treated effleunt for existing and proposed expansion and its adequacy. Status of dual plumbing system for existing occupancy further approved layout plan is not legible
Inspection: false
Inspection Note:
Officer: PPCB083
Reject: false
Reject Note:
Role: RO EE Kanwaldeep Kaur