Id: 31637483
Approve: false
Approve Note:
Clarification: true
Clarification Note: The application of the BKO was scrutinised and the following observations were made;- 1. The BKO to apply for the fresh CTO . 2. The BKO has not submitted the Bank Guarantee of amount Rs. 50,000 /- imposed vide ZO office letter no. 3434 on dated 21/05/2024. 3. The BKO has not submitted the completion certificate of the IDBKT technology. 4. The BKO has submitted the TDCO no. received from the PSPCL authorities after the disconnection of the electricity. You are requested to attend the above said observations within 02 days.
Date Created: 2026-04-01 18:02:08.539
File Note: The application of the BKO was scrutinised and the following observations were made;- 1. The BKO to apply for the fresh CTO . 2. The BKO has not submitted the Bank Guarantee of amount Rs. 50,000 /- imposed vide ZO office letter no. 3434 on dated 21/05/2024. 3. The BKO has not submitted the completion certificate of the IDBKT technology. 4. The BKO has submitted the TDCO no. received from the PSPCL authorities after the disconnection of the electricity. You are requested to attend the above said observations within 02 days.
Inspection: false
Inspection Note:
Officer: PPCB187
Reject: false
Reject Note:
Role: RO JEE Ajay Kumar