Show ApplicationProcessingDetails

Id: 31642848
Approve: false
Approve Note:
Clarification: true
Clarification Note: 1. The industry is required to apply as per latest categorization issued by CPCB. 2. The industry is required to submit proof regarding the production/ operation of the unit so as to justify the less operation of the unit during the months of January, May, July, August of 2025, within 02 days.
Date Created: 2026-04-02 11:36:07.211
File Note: 1. The industry is required to apply as per latest categorization issued by CPCB. 2. The industry is required to submit proof regarding the production/ operation of the unit so as to justify the less operation of the unit during the months of January, May, July, August of 2025, within 02 days.
Inspection: false
Inspection Note:
Officer: PPCB202
Reject: false
Reject Note:
Role: RO AEE Ishmanjot Singh