| File Note: |
On scrutinizing the application of the project proponent following observations were raised on 31.03.2026 with request to submit reply within 1 day.
1. In the application form, the project proponent has mentioned the address of the industry as Mubarikpur. However, as per the registry documents and the approved building plan, the address is recorded as Village Kheri. Therefore, the project proponent is required to apply for Consent to Operate using the correct address.
2. The address of the industry mentioned in the Certificate of In Principle Approval is mismatch with the address mentioned in the registry & building plan.
3. The certificate of Principle approval is issued for manufacturing of PVC water tank. However, the project proponent submitted manufacturing process of Rock-N-Roll Machine.
4. As per the manufacturing process, the category selected by the project proponent is incorrect. The site of industry was visited by AEE of this office on 01.04.2026 and it was observed that the applicable category of the industry is orange i.e. Reprocessing of waste plastic.
5. The project proponent is required to submit site suitability certificate from concerned department.
6. The project proponent has not mentioned complete correspondence address in the application form. The project proponent needs to change in the application form.
7. The project proponent has mentioned total investment cost is Rs. 23 lakh and plant and machinery cost is Rs. 6 lakh in the application form. However, as per the CA certificate, the total investment cost is Rs. 27.53 lakh and plant & machinery cost is Rs. 1.53 lakh. The project proponent needs to change in the application form.
8. The installation of the machinery was not completed. The industry is required to apply for prior Consent to establish (NOC) of the unit.
The application of the industry is returned.
|