Show ApplicationProcessingDetails

Id: 31733687
Approve: false
Approve Note:
Clarification: true
Clarification Note: The application was scrutinized and it was observed that: 1. The project proponent has not submitted a feasibility report for the proposed expansion. 2. The project proponent has not submitted the project report. As such, cost of project could not be verified. Adequacy of consent fee can be adjudged. 3. The PP has not linked any its NOC fee with the online application. 4. The project proponent has not mentioned the Last Consent Details in the application form. 5. The PP has not submitted its Environmental Clearance granted to it by competent authority as well as six month compliance report of the same. 6. The PP has also not submitted classification of land use/ change of land use of the area from Competent Authority. 7. The PP has not submitted building plans of its unit. The PP is required to submit buildings plans got approved from Competent Authority. 8. In the application form the PP has mentioned that waste water will be used onto land @ 4180 sqm for plantation but not submitted any details or documents regarding the same. 9. The PP has not submitted analysis report of the effluent sample by NABL approved laboratory. 10. The industry has uploaded Adhar Card instead of compliance report of conditions of ‘Consent to Operate’ varied granted by the Board. You are hereby request to clarify the same within 02 days, so that your application can be processed further.
Date Created: 2026-04-13 13:09:26.051
File Note: The application was scrutinized and it was observed that: 1. The project proponent has not submitted a feasibility report for the proposed expansion. 2. The project proponent has not submitted the project report. As such, cost of project could not be verified. Adequacy of consent fee can be adjudged. 3. The PP has not linked any its NOC fee with the online application. 4. The project proponent has not mentioned the Last Consent Details in the application form. 5. The PP has not submitted its Environmental Clearance granted to it by competent authority as well as six month compliance report of the same. 6. The PP has also not submitted classification of land use/ change of land use of the area from Competent Authority. 7. The PP has not submitted building plans of its unit. The PP is required to submit buildings plans got approved from Competent Authority. 8. In the application form the PP has mentioned that waste water will be used onto land @ 4180 sqm for plantation but not submitted any details or documents regarding the same. 9. The PP has not submitted analysis report of the effluent sample by NABL approved laboratory. 10. The industry has uploaded Adhar Card instead of compliance report of conditions of ‘Consent to Operate’ varied granted by the Board. You are hereby request to clarify the same within 02 days, so that your application can be processed further.
Inspection: false
Inspection Note:
Officer: PPCB224
Reject: false
Reject Note:
Role: RO AEE Savjot Singh Bains