| Id: | 31749223 |
| Approve: | false |
| Approve Note: | |
| Clarification: | true |
| Clarification Note: | The application was scrutinized and it was observed that the PP has mentioned different quantity of raw material in the application form than the quantity of raw material mentioned in the previous application on account of which consents were earlier granted to the industry but there is no change in the production capacity of the unit. This needs to be clarified. You are hereby request to clarify the same within 02 days, so that your application can be processed further. |
| Date Created: | 2026-04-15 11:21:55.134 |
| File Note: | The application was scrutinized and it was observed that the PP has mentioned different quantity of raw material in the application form than the quantity of raw material mentioned in the previous application on account of which consents were earlier granted to the industry but there is no change in the production capacity of the unit. This needs to be clarified. You are hereby request to clarify the same within 02 days, so that your application can be processed further. |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB224 |
| Reject: | false |
| Reject Note: | |
| Role: | RO AEE Savjot Singh Bains |