| Id: | 31983219 |
| Approve: | false |
| Approve Note: | |
| Clarification: | false |
| Clarification Note: | |
| Date Created: | 2026-05-12 13:05:50.944 |
| File Note: | As per RO report, the sampling of the unit may be carried out as per protocol sampling of the Board for which permissions are being taken from the CA and the industry has provided adequate sampling arrangements. Also the Compliance report in annotated form w.r.t SOP is attached,...........as per which the unit is complying with SOPs . Submitted as per earlier recommendations. The competency to decide the consent lies with Sr Environmental Engineer, Zonal Office-I, Ludhiana |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB126 |
| Reject: | false |
| Reject Note: | |
| Role: | ZO EE Sukhwant Singh |