Show ApplicationProcessingDetails

Id: 6810459
Approve: false
Approve Note:
Clarification: false
Clarification Note:
Date Created: 2017-12-05 12:01:31.118
File Note: Power Connection restore temporarily u/s 33-A for six month as reported by RO after visiting the industry on 21.11.2016 then EE RO visited the industry on 27.04.2017 and reported that industry is complying with the Water pollution norms accordingly electric connection further extended for six month on 22.05.2017. Now EE, RO visited the industry on 17.11.2017 and reported that industry is complying with the water pollution norms, considering the report submitted by RO may if approved consent to operate under water act be extended upto 30.06.2021 and electric connection restore permanently.
Inspection: false
Inspection Note:
Officer: PPCB027
Reject: false
Reject Note:
Role: ZO EE Joginder Singh