Show ApplicationProcessingDetails

Id: 7487545
Approve: false
Approve Note:
Clarification: true
Clarification Note: During scrutinizing the application, following discrepancies are observed: 1. The industry has not submitted documents regarding purchase of the industry. 2. The industry has not submitted land documents i.e. copy of registry of the land. 3. The industry has not submitted area clarification certificate issued from concerned authority, 4. The industry has submitted copy of approved building plan which is not readable. you are requested to submit above documents within 03 days positively to process the application.
Date Created: 2018-04-26 12:56:12.782
File Note:
Inspection: false
Inspection Note:
Officer: PPCB122
Reject: false
Reject Note:
Role: RO JEE VINOD KUMAR