| File Note: |
The details as per the record are as follows :- The industry was established with consent to establish of the Board vide CTE no. ZO-JAL/RM/BAT/NOC/2010/-206 dt 30-03-2010, thus fulfilling the siting guidelines. The industry was commissioned in year 2010. The industry has installed ETP for the treatment of effluent generated from saila plant. The quantity of treated trade effluent is 160 KLD. The industry has provided plantation of eucalyptus trees as per karnal technology in area measuring 2 aces for disposal of treated trade effluent.
Further the industry has submitted that the industry is not in operation from past two years. This is for your information please.
|