Show WasteManagementProcessingDetails

Id: 26151281
Application For: BMW
Application Id: 26092277
Approve: false
Approve Note:
Clarification: false
Clarification Note:
Date Created: 2024-07-05 17:00:32.199
File Note: As discussed, The HCF has not installed ETP cum STP plant for treatment of its effluent and the HCF falls beyond the limit of terminal STP. Therefore, HCF is required to install ETP cum STP plant for treatment of its effluent. As such application of authorization under BMW Rules, 2016 is required to return to the HCF. There is no option to return the application in my portal, as the scrutiny is completed. Keeping the above in view, the application is required to return to the HCF, please.
Inspection: false
Inspection Close: false
Inspection Close Note:
Inspection Note:
Last Updated: 2024-07-05 17:00:32.199
Officer: PPCBOS16
Officer Fwd: PPCB064
Reject: false
Reject Note:
Role: RO AEE OS Jaspreet Kaur
Role Fwd: RO EE Gurmeet Singh