| File Note: |
While scrutinized the case it has been observed that: -
1. The authorization form submitted by the industry is incomplete.
2. The industry has not submitted the dimensional Drawing of Hazardous waste Storage Room.
3. The industry has applied for authorization only cat.No. 5.1, whereas, industry was required to apply for authorisation of Hazardous waste of remaining categories also which are applicable.
The applicant is requested to clarify the above so that further action in the matter can be taken, please.
|