The industry is required to submit the compliance of personal hearing decisions held before the Senior Environmental Engineer of the Board on 19.02.2026 decided as under:
1. The industry shall reassess the effluent quantities and make revised agreement with CETP operator, if required, as per the actual generation of effluent and submit the same to the Board, within 07 days.
2. The industry shall increase the capacity of effluent collection tank, at least equivalent to the CETP agreement, by providing additional storage tank, within 07 days.
3. The industry shall prepare a revised lifting schedule with the CETP operator and to ensure that the lifting shall be made atleast 2-3 times in a month and take a written assurance from the operator.
4. The industry shall install CCTV cameras with 30 days backup within 07 days, facing towards
a. entry gate of processing shed
b. flow meter provided on freshwater supply provided for processing activities
c. effluent storage tanks
d. any other suitable point deemed fit to ensure that whole of the water consumed is metered and whole of the trade effluent is lifted to CETP operator
The industry shall maintain in-house monitoring mechanism through mobile phone/ office screen for visualizing the above CCTV cameras so as to ensure that no intentional or unintentional lapse happens and no untreated effluent is bye-passed.
5. The industry shall ensure that there is no unauthorized mode of wastewater disposal. 6. The industry shall ensure that there is only a single fresh water supply for the industry and meters shall be provided for the water being used for process.
6. The industry shall maintain proper record of fresh water consumption and trade effluent generated & effluent got lifted by the CETP operator on daily basis.
7. The record shall be available in the industry at all times, kept in a designated box in the process area to ensure easy and ready accessibility to record keeper as well as regulatory authority. In case, the record is not maintained by the industry, it will be presumed that the industry is disposing of its wastewater illegally and action as deemed fit shall be taken in accordance with law.
8. The industry shall apply for consent to operate under the Water Act, 1974 and the Air Act,1981 within 07 days.
9. The Environmental Engineer, Regional Office-4, Ludhiana shall visit the industry immediately after 07 days, to verify contentions of the industry, carry out audit of the waste water generation, process consent applications on merit and submit compliances with respect to the decisions alongwith fresh recommendations. If the industry fails to comply with the decisions of personal hearing within stipulated time period, further action be processed immediately.
|