| 30991204 |
false |
|
true |
The application was scrutinized and it was observed that:
1. The project proponent has still not submitted the revised water calculation as per the NBC norms. The waste water proposed for being utilized for flushing purpose is also on the higher side and not as per the prescribed NBC norms.
2. Further, the project proponent proposes to develop green area as per karnal technology in 5679 sqmtr (1.4 acre) and proposes to treat 178 KLD waste water in the same which is not adequate.
Therefore, the project proponent request to clarify the same within 02 days, so that your application can be processed further.
|
2026-01-23 12:59:55.991 |