| 21680653 |
false |
|
false |
1 A final target date of completion of STP rehabilitation project
REPLY - It has been completed on dt 30-11-2022
2 The date by which the rehabilitated STP will be stabilized and start giving desired results so that sampling process can be started.
REPLY - 15-12-2022
3 Pert chart ( stage/ component/ activity wise ) of rehabilitation and stabilization of STP.
REPLY - Completed (Not Applicable)
4 Can't allow treated effluent discharge into river Satluj for indefinite time . Proposal for utilization of treated effluent.
REPLY - Plan for utilization of treated water by Soil and Water Conservation Department, Punjab is under progress |
2023-04-04 20:27:53.871 |