
| Id | Approve | Approve Note | Clarification | Clarification Note | Date Created |
|---|---|---|---|---|---|
| 30998334 | false | false | 2026-01-24 14:22:16.039 | ||
| 30998337 | false | false | 2026-01-24 14:22:30.577 | ||
| 30998340 | false | false | 2026-01-24 14:22:54.646 | ||
| 30999866 | false | false | 2026-01-24 19:48:33.115 | ||
| 31000541 | false | false | 2026-01-25 12:19:20.91 | ||
| 31001435 | false | false | 2026-01-25 18:32:28.717 | ||
| 31001994 | false | true | The application of the project was scrutinized and it has been observed that the project proponent has not submitted any certificate obtained from the concerned authorities regarding adequacy of the terminal STP to handle the surplus pollution load of the colony. It is therefore requested to submit reply of the clarification within 02 days. | 2026-01-26 10:04:35.317 | |
| 26891516 | false | false | 2024-09-16 13:23:17.863 | ||
| 31002292 | false | false | 2026-01-26 11:14:37.217 | ||
| 31002990 | false | false | 2026-01-26 13:38:14.706 |