| 25574560 |
false |
|
true |
The application was scrutinized and observed that the industry is required to submit concrete proof of date of commissioning, so as to adjudged the adequacy of consent fee submitted by the industry.
You are requested to submit the same within two day.
|
2024-05-03 12:18:12.138 |
| 25574575 |
false |
|
false |
|
2024-05-03 12:18:22.084 |
| 25574598 |
false |
|
true |
The application was scrutinized and observed that the CA certificate submitted by the industry mentioned plant and machinery value with depreciation, the industry is required to submit CA certificate gross block value of fixed assets without depreciation.
You are requested to submit the same within two day.
|
2024-05-03 12:19:20.651 |
| 25673538 |
false |
|
true |
Please deposit consent fees within two days. |
2024-05-15 20:41:06.226 |
| 25768231 |
false |
|
false |
|
2024-05-27 12:13:57.34 |
| 25768238 |
false |
|
false |
|
2024-05-27 12:14:07.193 |
| 25865688 |
false |
|
true |
The application was scrutinized and it was observed that the industry has not mentioned the treatment details of domestic wastewater generated in the application form. As such, you are requested to remove the above said observations within 03 days, so that the application can be processed further. |
2024-06-06 22:19:55.712 |
| 25945283 |
false |
|
true |
CA certificate submitted by the industry is quite old. Get latest CA certificate showing gross block of fixed assets ( without depreciation) including value of land and building. |
2024-06-18 12:36:48.139 |
| 25945290 |
false |
|
true |
CA certificate submitted by the industry is quite old. Get latest CA certificate showing gross block of fixed assets ( without depreciation) including value of land and building. |
2024-06-18 12:37:04.359 |
| 26015778 |
false |
|
false |
|
2024-06-25 12:35:41.407 |