| 21005166 |
false |
|
true |
As per record, the industry has installed 4 no. power presses and 1 no. shot blasting machine. As per the fixed assets addition details, the industry has submitted that it has installed 2 no. power presses, 1 no. shot blast and 1 no. electrical transformer, which indicates towards increase in the production capacity of the unit. The industry has not provided any details of equipment related to installation of PNG and the cost related to it. As per the CA certificate, the land taken is on lease and the industry is required to submit lease deed alongwith application. The industry has not deposited penalty fee (25%) alongwith the application.
The industry is required to clarify the above within 2 days. |
2023-01-28 14:37:22.285 |