While scrutinize the case it has been observed that:-
(1) Earlier, the Total Land area of the industry was 11700 Sq. Meters, Now the total land area of the industry is 15133 Sq. Meters, the industry has not submitted CLU/Land use pattern of the industry.
(2) The industry has made an extension in Power Load from 999.206 KW to 1999 KW without obtaining NOC of the Board.
(3) The industry has not submitted the feasibility report of ZLD .
(4) The industry has not submitted the record regarding operation of ETP/ZLD and chemicals consumption.
(5) The industry has not submitted the Analysis report of treated trade effluent and treated domestic effluent from the Boards Lab.
(6) The consent fee deposited by the industry is not adequate for next 5 years, as the industry is required to deposit the balance consent fee on the basis of fixed assets increased year to year basis including late fee.
(7) The industry has not submitted by the compliance report of previous consent conditions and NOC conditions if would have been obtained by the industry prior to expansion.
(8) Please submit the copy of Plastic Waste Registration obtained by the industry.
(9) Please submit the details of arrangement provided for handling of Solid Waste generated by the industry.
(10) As the ETP based on ZLD technology has been commissioned. Hence, the industry is also required to apply for varied authorisation under the Hazardous and Other Wastes (Management and Transbounary Movement) Rules, 2016.
You are requested to attend the above said observations and submit your reply within 2 days.
|