| 20400418 |
false |
|
false |
|
2022-11-14 21:15:18.071 |
| 20427307 |
false |
|
false |
|
2022-11-17 14:18:22.541 |
| 20436138 |
false |
|
false |
|
2022-11-18 13:18:38.398 |
| 20436171 |
false |
|
true |
The application of the Industry has been scrutinized and it is observed as under:
1. Earlier, the industry had submitted its CA certificate dated 15.05.2017, wherein, total value of assets was mentioned as Rs. 30.50 lakhs. Now, the industry has uploaded a copy of CA certificate dated 07.03.2022, wherein, total value of assets have been mentioned as Rs. 64.68 lakh. As such, there is huge increase in value of assets of the industry, which needs clarification.
2. The industry has not uploaded a copy of stack emission sampling results carried out by approved laboratory.
As such, the industry is required to clarify regarding above within 03 days, so that further action may be taken in the matter, please.
|
2022-11-18 13:21:02.344 |
| 21113557 |
true |
|
false |
|
2023-02-09 12:38:50.739 |
| 20436183 |
false |
|
true |
The application of the Industry has been scrutinized and it is observed as under:
1. Earlier, the industry had submitted its CA certificate dated 15.05.2017, wherein, total value of assets was mentioned as Rs. 30.50 lakhs. Now, the industry has uploaded a copy of CA certificate dated 07.03.2022, wherein, total value of assets have been mentioned as Rs. 64.68 lakh. As such, there is huge increase in value of assets of the industry, which needs clarification.
2. The industry has not uploaded a copy of stack emission sampling results carried out by approved laboratory.
As such, the industry is required to clarify regarding above within 03 days, so that further action may be taken in the matter, please.
|
2022-11-18 13:21:20.272 |
| 20436197 |
false |
|
true |
Show cause notice for refusal of renewal of CTOs under Water Act, 1974 and Air Act, 1981 has been issued to the industry vide no. 3112 dated 18/11/2022 to file written reply before the Worthy CEE of the Board within 15 days from the date of issuance of notice. A copy of the same is attached herewith for information & necessary action. Failing which, it shall be presumed that the industry has nothing to say and Board shall go ahead to take proposed action in the matter without giving any further notice/ opportunity. |
2022-11-18 13:22:05.05 |
| 21236638 |
false |
|
false |
|
2023-02-23 15:30:16.59 |
| 20447660 |
false |
|
false |
|
2022-11-21 10:55:04.436 |
| 20447665 |
false |
|
false |
|
2022-11-21 10:55:14.66 |