4. The PP has deposited the consent fee of Rs. 1,44,00/- @ Rs.28,800/- PA for 5 years), whereas the PP is required to deposit Rs.42000/- P.A. due to increased fixed assets as per Sr.No. 2 above - A total fee of Rs.2,88,000 was paid for Air (Dated:15.03.2024) and Water (Dated:20.02.2024). As per the revised project cost, the difference amount of Rs. 48000 was paid for both Air and Water on 30th April 2024, the receipts of which has been uploaded.
Please find the below mentioned points for Compliance of the decisions of personal hearing taken by Senior Environmental Engineer, Zonal Office-I, Ludhiana on 15.04.2024:
a.The industry shall close soakage pit immediately - Soak pit has been isolated and closed completely.
b.The industry shall develop proper plantation area for discharge of domestic effluent - 5000 sq ft area developed for greenery and further development of about 2000 Sq ft is under process.
c. The industry shall provide proper sampling arrangements with stack of adequate height, within 07 days - Proper sampling arrangements have been made with appropriate platforms and handrailing. |